Lewistown Southeast
Contracting Agency: Montana Department of Transportation
Completion Date: 2016
The work consisted of 5 miles of Roadway Reconstruction. Major items include 125,000 Cubic Yards of Excavation, 40,000 Cubic Yards of Special Borrow, 22,000 Cubic Yards of Cement Treated Base, 4,000 Cubic Yards of Base Course, 20,000 Tons of Asphalt Plant Mix, 1,500 Square Yards of MSE Wall, 450 Square Yards of Soil Nail Wall, 4,400 Square Feet of Sheet Pile Wall, and Installation of 2 Reinforced Soil Slopes.