Contracting Agency: Idaho Transportation Department
Total Contract: $40,000,000
Completion Date: 2009
Worley North is a continuation of the Setters to Bellgrove project that we had previously completed. This project consisted of the realignment of 5 miles of U.S. Highway 95 and construction of the Highway 95 and SR 58 interchange. The majority of our work includes 1,405,000 cubic meters of excavation, placement of 377,541 metric ton of rock cap, 133,200 metric ton of rock armor, 124,337 metric ton of drain rock.